Richardson Facades partition wall & electrical works
Project details
186 were delighted to deliver a partition wall removal and electrical reconfiguration project for Richardson Facades Limited.
The initial phase involved the safe removal and disposal of an existing partition wall, followed by repairs to the existing wall surfaces.
We supplied and fitted a new section of skirting board and made good the existing floor tiles, fitting new ones where necessary as supplied by the client.
Throughout the process, the team maintained a clean and safe environment by providing full floor protection and managing the removal of all waste materials via a skip.
Electrical works included stripping out of existing works. We relocated the dado trunking, along with all power sockets and data outlets, onto the adjacent wall. Additionally, the light switch was relocated onto the trunking for better accessibility.
Project status – Completed on time and within budget.
Project Manager – Chris Lakey
Contract duration – 5 days
Form of tender – Enquiry
Sector – Offices & Electrical
Site contact – P. Baynham


Summary of works